EPS@ISEP | The European Project Semester (EPS) at ISEP

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revisionPrevious revision
Next revision
Previous revision
plan [2022/03/30 11:46] – [Project Plan] team5plan [2022/06/08 12:30] (current) – [Deadlines] epsatisep
Line 10: Line 10:
   * 2022-04-14 Upload the **Interim Report and Presentation** to the wiki. The report must contain the the following chapters: Introduction, Project Management, State of the Art, Marketing Plan, Eco-efficiency Measures for Sustainability, Ethical and Deontological Concerns, Proposed Solution and Bibliography. In particular, the Project Management chapter includes the updated project progress register, the sprint report for completed sprints (tasks that were included, statuses, assignees, allocations) and the updated release Gantt chart    * 2022-04-14 Upload the **Interim Report and Presentation** to the wiki. The report must contain the the following chapters: Introduction, Project Management, State of the Art, Marketing Plan, Eco-efficiency Measures for Sustainability, Ethical and Deontological Concerns, Proposed Solution and Bibliography. In particular, the Project Management chapter includes the updated project progress register, the sprint report for completed sprints (tasks that were included, statuses, assignees, allocations) and the updated release Gantt chart 
   * 2022-04-21 Interim Presentation, Discussion and Peer, Teacher and Supervisor Feedbacks   * 2022-04-21 Interim Presentation, Discussion and Peer, Teacher and Supervisor Feedbacks
-  * 2022-04-27 Upload the final **List of Materials (local providers & price, including VAT and transportation)** to the wiki+  * 2022-04-27 Upload the final **List of Materials (local providers & price, including VAT and transportation)** and the **3D Model Video** to the wiki
   * 2022-05-14 Upload refined Interim Report (based on Teacher & Supervisor Feedback)   * 2022-05-14 Upload refined Interim Report (based on Teacher & Supervisor Feedback)
 +  * 2022-05-26 Upload **packaging solution** to Deliverables and Report
 +  * 2022-06-07 Upload the results of the **Functional Tests** to the wiki
   * 2022-06-07 Upload the results of the **Functional Tests** to the wiki   * 2022-06-07 Upload the results of the **Functional Tests** to the wiki
   * 2022-06-18 Upload the **Final Report, Presentation, Video, Paper, Poster and Manual**   * 2022-06-18 Upload the **Final Report, Presentation, Video, Paper, Poster and Manual**
Line 21: Line 23:
   * 2022-06-30:   * 2022-06-30:
     - Hand in the **prototype and user manual** to the client     - Hand in the **prototype and user manual** to the client
 +    - Do a **live demo** of the prototype
     - Receive the **EPS@ISEP certificate**     - Receive the **EPS@ISEP certificate**
-    - Bring **typical food** from your country+    - Bring and share **typical food** from your country
  
  
Line 62: Line 65:
 <WRAP box 400px center> <WRAP box 400px center>
 ^ PBI       ^ Title          ^ Status     ^ ^ PBI       ^ Title          ^ Status     ^
-| A         | Define project backlog, Gantt chart,...    | To do         +| A         | Define project backlog, Gantt chart,...    | done         
-| B         | Research and inspiration   To do            +| B         | Research and inspiration   done            
-| C         | Defining Topic | To do      |    +| C         | Defining Topic | done     |    
-| D         | Blackbox To do         +| D         | Blackbox done         
-| E         | List of materials 1 | To do      |    +| E         | List of materials 1 | done     |    
-| F         | System systematics & structural drawings    | To do      |    +| F         | System systematics & structural drawings    | done     |    
-| H         | Cardboard scale model    | To do      |    +| H         | Cardboard scale model    | done     |    
-| I         | Interim report and presentation    | To do      |    +| I         | Interim report and presentation    | done     |    
-| J         | List of materials and composer | To do      |   +| J         | List of materials and composer | done    |   
 | K         | Functional tests   | To do      |    | K         | Functional tests   | To do      |   
-| L         | Final report | To do      |  +| L         | Final report | In progress     |  
-| M         | Final presentation To do      |+| M         | Final presentation In progress     |
 | N         | Doing the final presentation | To do      |    | N         | Doing the final presentation | To do      |   
-| O         | Flyer (work times undecided)   To do         +| O         | Flyer (work times undecided)   in progress         
-| P         | Leaflet (work times undecided)    | To do      |    +| P         | Leaflet (work times undecided)    | In progress to be refined    |    
-| Q         | 3D model (work times undecided)    | To do      |   +| Q         | 3D model (work times undecided)    | in progress     |   
 | R         | Packaging (work times undecided) | To do      |    | R         | Packaging (work times undecided) | To do      |   
-| S         | Paper (work times undecided)   To do         +| S         | Paper (work times undecided)   In progress         
-| T         | Poster (work times undecided) | To do      |  +| T         | Poster (work times undecided) | In progress      |  
-| U         | Code (work times undecided) To do      |+| U         | Code (work times undecided) In progress      |
 | V         | Manual (work times undecided) | To do      |  | V         | Manual (work times undecided) | To do      | 
-| W         | Video (work times undecided) To do      |+| W         | Video (work times undecided) In progress    |
 </WRAP> </WRAP>
 </table> </table>
Line 145: Line 148:
 <WRAP box 400px center> <WRAP box 400px center>
 ^ Sprint    ^ PBI   ^ Responsible  ^ Involved   ^ Status      ^ ^ Sprint    ^ PBI   ^ Responsible  ^ Involved   ^ Status      ^
-| 1         | A, B, C, D, I     | Jacobine, Julia, Julian, Gema      | J, J, J, G | In progress        |  +| 1         | A, B, C, D, I     | Jacobine, Julia, Julian, Gema      | J, J, J, G | Done        |  
-| 2         | D, E, F, H, I, J     | Jacobine, Julia, Julian, Gema  | J, J, J, G | To do             +| 2         | D, E, F, H, I, J     | Jacobine, Julia, Julian, Gema  | J, J, J, G | Done             
-| 3         | E, H, I, L     | Gema, Julian, Jacobine   | J, J, J, G | To do        |  +| 3         | E, H, I, L     | Gema, Julian, Jacobine   | J, J, J, G | Done       |  
-| 4         | E, H, I, J, L     | Jacobine, Julia, Julian, Gema | J, J, J, G | To do        |  +| 4         | E, H, I, J, L     | Jacobine, Julia, Julian, Gema | J, J, J, G | Done      |  
-| 5         | J, L     | Jacobine, Julian      | J, J, J, G | To do |   +| 5         | J, L     | Jacobine, Julian      | J, J, J, G | Done |   
-| 6         | J, L     | Jacobine, Julian      | J, J, J, G | To do +| 6         | J, L     | Jacobine, Julian      | J, J, J, G | Done 
-| 7         | L, K     | Julian, Julia      | J, J, J, G | To do |+| 7         | L, K     | Julian, Julia      | J, J, J, G | In progress |
 | 8         | L, K     | Julian, Julia   | J, J, J, G | To do        |  | 8         | L, K     | Julian, Julia   | J, J, J, G | To do        | 
 | 9         | L, K     | Julian, Julia  | J, J, J, G | To do        |      | 9         | L, K     | Julian, Julia  | J, J, J, G | To do        |     
Line 166: Line 169:
 <WRAP centeralign> <WRAP centeralign>
 <figure flabel1> <figure flabel1>
-{{ :schermafbeelding_2022-03-15_om_15.12.14.png?nolink&600 |}} +{{ :gantt_chart_13.04.22.jpg?nolink&600 |}} 
-{{ ::gantt-chart_eps_group_5.xlsx |}}+{{ ::t5_dstrs_gantt_chart.xlsx |}}
 <caption>Release Gantt chart</caption> <caption>Release Gantt chart</caption>
 </figure> </figure>
Line 209: Line 212:
 <WRAP centeralign> <WRAP centeralign>
 <figure flabel2> <figure flabel2>
-{{ ::blackbox_oortjes_tekengebied_1.png?nolink&400 |}}+{{ :t5_dstrs_blackbox_official_final_version_tekengebied_1.jpg?nolink&600 |}}
 <caption>Blackbox product</caption> <caption>Blackbox product</caption>
 </figure> </figure>
QR Code
QR Code plan (generated for current page)